Software handover checklist: what to get when a project ends

Hephaestus Technology7 min read

A software handover checklist is the list of everything you must receive from a development partner so that another team can run, change and own your software without them. At minimum that means the full source code and build scripts, every account and credential, documentation, a signed IP assignment, details of third-party services and licences, and confirmation of what happened to personal data. The best time to agree the list is when you sign the contract; the second best is now, before the relationship ends.

Key takeaways

  • Ownership needs paperwork: in Ireland a copyright assignment is only effective in writing and signed.
  • Collect access, not just files: repositories, cloud, domains, app stores and third-party services should be in your company's name.
  • Ask for documentation a new developer could follow to build and deploy the system from scratch.
  • Under the GDPR, a processor must delete or return personal data at your choice when its services end.
  • Verify the handover by having someone independent rebuild and deploy the software before the final payment.

When do you need a software handover?

You need a handover whenever responsibility for your software moves: at the end of a fixed-price project, when you switch agencies, when you bring development in-house, or when a key freelancer leaves. A partial version is also worth doing at each major milestone, so a full handover never becomes a crisis.

Start with the paperwork, because without it the rest may not be yours.

  • Signed IP assignment. Under Irish law the author is the first owner of copyright unless the work is made by an employee, and an assignment is not effective unless in writing and signed. Check that the contract contains a present assignment, or get a confirmatory assignment signed now.
  • Subcontractor assignments. Confirmation that freelancers and subcontractors assigned their rights to the agency, so the chain of ownership is complete.
  • Background IP licence. A written licence for any of the supplier's own tools or libraries embedded in your product.
  • Open source inventory. A list of open source components and their licences. The Open Source Initiative lists approved licences, and obligations vary between them.
  • Confirmation of payment status and any outstanding obligations on either side.

For the clauses themselves, see our explainer on who owns the code in software development contracts.

What code and build items should you get?

Get everything needed to rebuild the software from nothing, not just the application code.

  • Complete source code with full version history, in a repository your company owns. Transfer of the repository is better than a zip file, because history explains decisions.
  • All branches and tags, including unreleased work, with a note on which branch is in production.
  • Build and deployment scripts, CI/CD pipeline configuration and infrastructure-as-code files.
  • Dependency lists and lock files, ideally as a software bill of materials, which CISA describes as a nested inventory of the components that make up software. Our explainer on what an SBOM is covers formats.
  • Mobile signing keys and certificates, plus instructions for publishing updates. Losing an app signing key can prevent you from updating your own app.
  • Database schema and migration scripts.
  • Automated tests and instructions to run them.

Which accounts and credentials must be transferred?

Every account that runs or controls the product should end up owned by your company, with the supplier's access removed.

Account type Examples What to confirm
Code and project tools Repository, issue tracker, documentation space Company is owner; supplier access removed or reduced
Cloud and hosting Cloud provider accounts, CDN, DNS Billing in company name; root or owner access held by you
Domains Registrar accounts Registrant is your company; renewal dates noted
App stores Apple and Google developer accounts Enrolled under your company, not the agency
Third-party services Payments, email, analytics, monitoring, AI APIs Contracts and API keys in your name; keys rotated
Secrets Passwords, API keys, certificates Moved to your password manager or secrets vault, then rotated

Rotate every password and key after handover. Credentials that passed through many hands should be treated as known to all of them.

What documentation should be included?

Ask for documentation a competent new developer could follow without calling the previous team.

  • Architecture overview: components, how they connect, and where each runs.
  • Setup guide: how to run the system locally and in test.
  • Deployment and rollback procedure.
  • Environment and configuration reference, without secrets in plain text.
  • Operational runbook: monitoring, alerts, backups and how to restore them, common incidents.
  • Known issues and technical debt, including anything deliberately left unfinished.
  • Decision log: why key technical choices were made.
  • API documentation for internal and external interfaces.

What happens to data at the end of the project?

Data held by the supplier should be returned or deleted, on your instruction. If the supplier processed personal data on your behalf, the GDPR requires that it, at the choice of the controller, deletes or returns all the personal data after the end of the services and deletes existing copies, unless law requires storage (Article 28(3)(g)).

Collect:

  • copies of any production or test data you need;
  • written confirmation of deletion of the rest, including backups and developer laptops;
  • a list of any sub-processors who also held data, and confirmation they have done the same.

How do you transfer knowledge, not just files?

Knowledge transfer happens through people, so schedule it. Agree:

  1. Walk-through sessions covering architecture, code structure, deployment and operations, recorded for later.
  2. Shadowing, where your new team performs a deployment while the outgoing team watches, and then the reverse.
  3. A support window after handover, such as a few weeks of paid, time-boxed availability for questions.

If the new team is in another time zone, use the written handoff habits from our guide to running a remote development team.

How do you verify the handover is complete?

Verify by doing, not by reading a list. Have your new team, or an independent developer, clone the repository, build the system, deploy it to a fresh environment and run the tests, using only the documentation provided. Anything they cannot do is a gap. Tie the final payment or retention release to this check, and record sign-off in writing.

What does the full checklist look like?

Copy this list into your contract schedule or project tracker.

  • [ ] Signed IP assignment, including subcontractors
  • [ ] Background IP licence and open source inventory
  • [ ] Repository with full history transferred to company ownership
  • [ ] Build, deployment, CI/CD and infrastructure-as-code files
  • [ ] Mobile signing keys and certificates
  • [ ] Cloud, domain, app store and third-party accounts in company name
  • [ ] All secrets moved to your vault and rotated
  • [ ] Architecture, setup, deployment, runbook and API documentation
  • [ ] Known issues and decision log
  • [ ] Personal data returned or deleted, with written confirmation
  • [ ] Knowledge transfer sessions held and recorded
  • [ ] Independent rebuild and deploy completed successfully
  • [ ] Supplier access removed

This checklist is general information, not legal advice; ask a solicitor to review any termination or assignment documents.

Frequently asked questions

When should I agree the handover terms?

At the start, in the contract. Include a handover schedule listing deliverables, a timeline and an obligation to cooperate after termination. Suppliers are more willing to agree detailed exit terms before work begins than at the end of a strained relationship.

Can an agency refuse to hand over the code?

It depends on the contract and on whether copyright has been assigned to you. If there is no written assignment, the agency may still own the code. Disputes often arise over unpaid invoices, so keep payments current and take legal advice early if a supplier withholds code.

How long should a handover take?

It depends on the size of the system, but plan for at least a few weeks for a typical startup product, including walk-throughs, shadowed deployments and verification. A rushed handover in the last days of a contract usually leaves gaps.

Do I need the full Git history or just the latest code?

Get the full history if you can. It shows who changed what and why, helps the new team understand decisions, and supports IP due diligence later. A snapshot of the latest code is a poor substitute.

What if the previous developer used my data for testing?

Ask for written confirmation that the data has been deleted or returned, including from backups and personal devices. If they processed personal data on your behalf, the GDPR requires them to delete or return it at your choice when the services end.

Changing development partner or bringing work in-house? Book a free 30-minute call and we will help you plan a clean handover.

Cover photo by RDNE Stock project on Pexels.

Hephaestus Technology

We help founders and businesses validate, build and launch products across software, AI and hardware, from offices in Ho Chi Minh City, Dublin and Delaware. See how we work.

Tell us what
you're building.

A free 30-minute call. You'll get an honest view of the idea, the risks we see and what we'd do first, whether or not we end up working together.